PowerStudio

Guide · 1.2.0

Get started

This chapter takes you through a first session with PowerStudio, from opening a network to running every kind of study on it. It takes about 30 minutes. You do not need to read the other chapters first. Each step points to the chapter that explains more.

You will work on the IEEE 14-bus sample, a 132/33/11 kV transmission network that comes with the app. A busbar is a point where lines, transformers, machines and loads connect. The sample has 14 of them. A branch is a line or a transformer.

You will:

  1. Open the sample
  2. Run a load flow
  3. Change element data
  4. Set up winter and summer study cases
  5. Calculate short-circuit currents
  6. Check the network for single outages
  7. Simulate a fault and its clearing
  8. Look at the first cycles of the fault
  9. Export and compare results

At the end, a table shows where to start each study.

Before you start

Open the app at https://swiftugandan.github.io/powerstudio/app/. To work offline, open PowerStudio.html from the latest release. Use a recent desktop browser. PowerStudio is tested in Chromium, Firefox and WebKit, the engines behind Chrome, Edge, Firefox and Safari.

The guide gives keyboard shortcuts for Windows and Linux. On a Mac, use ⌘ for Ctrl and ⌥ for Alt.

You do not need an account. Your networks and results stay on your device, and PowerStudio saves your work as you go.

Open the sample

The first time you open PowerStudio, it opens the IEEE 14-bus sample for you. If you have used it before, or you want to start again, open a fresh copy:

  1. Go to the Help tab.
  2. Select IEEE 14-bus system.

A fresh copy means you cannot break anything. The Help tab also has Getting started, which opens this chapter, and Guide, which opens the contents page. The second sample, Riverside distribution, is a 110/20/0.4 kV network with a cable ring and a combined heat and power (CHP) unit.

The screen has 5 parts:

To find any command or element by name, press Ctrl+K and start typing.

Read more in Build your network.

Run a load flow

A load flow calculates the voltage at every busbar and the power through every branch, for one operating point.

  1. Go to the Home tab.
  2. Select Load flow, or press Alt+L.

PowerStudio shows the results in 2 places:

The sample has 259.00 MW of load, so the tab shows Load 259.00 MW.

The Load flow tab has 3 views: Busbars, Branches and Machines and loads. Select a column heading to sort by it. Select a row to find the element on the diagram.

To show only the rows that need attention:

Show a chart. The Busbars and Branches views have a Table / Chart switch. Select Chart to see the same rows as bars. The busbar chart shows each voltage around 1 per unit, with the allowed band shaded. The branch chart ranks the loadings against 90 % and 100 %. Select a bar to select its element. Select Table to go back. The Short circuit and Contingency tabs have the same switch.

Read more in Run a load flow and Work with results.

Change element data

  1. On the diagram, select Load 3, the load on Bus 3. You can also press Ctrl+K and type Load 3.
  2. In the inspector, change Active power from 94.2 to 120 MW.
  3. Press Enter.

The load flow runs again by itself, because Recalculate on edit is on. The total load is now Load 284.80 MW.

To undo the change:

  1. Select an empty part of the diagram.
  2. Press Ctrl+Z.

The total load goes back to 259.00 MW.

If you switch off Recalculate on edit, PowerStudio marks results that no longer match the network as Calculated before the last edit. They stay marked until you run the calculation again. You find the switch on the Calculate tab, under Steady state.

Every field shows its unit. Hover over a field's name to see what it means. If you type a value that is out of range, PowerStudio refuses it, tells you why and keeps the old value.

To change many elements at once, open the Data tab in the results panel. It shows every element of one kind as a table. You can change several cells together, or paste a block of cells from a spreadsheet.

Read more in Enter element data.

Set up winter and summer study cases

A study case is one set of conditions to study the network under. It has:

You will keep the sample's values as a winter peak. Then you will add a summer minimum, with less load and one generator switched off.

First, create the 2 study cases:

  1. Select the study case in the title bar. It says Base case.
  2. Select Manage project….
  3. Under Study cases, rename Base case to Winter peak.
  4. Under Scenarios, select New scenario.
  5. Rename the new scenario to Summer minimum.
  6. Under Study cases, select New study case. It starts as a copy of Winter peak.
  7. Rename the new study case to Summer minimum.
  8. Choose Summer minimum as its Scenario.
  9. Select the radio button beside Summer minimum to make it the active study case.
  10. Select Back to diagram. The title bar now says Summer minimum.

Then change the summer conditions:

  1. Press Ctrl+, to open the study case settings.
  2. Under Load flow, set Load scaling to 60 %.
  3. Select Apply.
  4. Select Generator 2, on Bus 2.
  5. Press Shift+O to switch it out of service. It is greyed out on the diagram.
  6. Run the load flow (Alt+L). The total load is now Load 155.40 MW.

With less load, the voltages on the 33 kV network rise. Several busbars are now above their upper limit and show red on the diagram. Select Outside band in the Busbars view to list them.

PowerStudio keeps the load scaling in the summer study case, and the generator's state in the summer scenario. Winter peak still has all its load and every generator. To switch between the 2, select the study case in the title bar and choose the one you want.

Read more in Set up study cases, scenarios and variants.

Calculate short-circuit currents

A short circuit study calculates the current that flows into a fault at each busbar. You use it to check switchgear ratings. The calculation is IEC 60909-style: it follows the method of IEC 60909-0 but is not certified against the standard.

  1. Switch back to the Winter peak study case.
  2. Go to the Calculate tab.
  3. Under Faults, select Three-phase.
  4. Under Faults, select Maximum currents.
  5. Select Short circuit, or press Alt+S.

PowerStudio applies a fault at every busbar in turn. The Short circuit tab lists these currents at each busbar:

To see where the current at one busbar comes from:

  1. Right-click Bus 4 on the diagram.
  2. Select Short circuit at this busbar.
  3. In the Short circuit tab, select Contributions.

The table lists the current in every line and transformer, at each end. You can also select a busbar and run Short circuit at selected busbar from the command palette (Ctrl+K). Contributions appears only for a three-phase fault at 1 busbar.

To go back to a fault at every busbar, select Every busbar under Faults.

Read more in Find fault levels. The method is in the short circuit section of the engine reference.

Check the network for single outages

An N-1 analysis takes each line and transformer out of service in turn. It then checks the network still works.

On the Calculate tab, select Contingency, or press Alt+N.

PowerStudio runs a load flow for each outage. The Contingency tab lists every outage, whether its load flow solved, and the violations it causes. A violation is a branch loaded above its limit or a busbar voltage outside its band. The tab only counts violations that the base case does not already have.

On the sample, the tab says 10 contingencies with new violations. The diagram shows the worst result for each element.

To include generator outages, select Generator outages under Security before you run it. To study several elements out at once, or to add remedial actions, select Contingencies.

Read more in Check the network survives outages.

Simulate a fault and its clearing

A stability simulation shows whether the machines stay in step with each other after a disturbance. It follows the swings over a few seconds.

The sample already has a disturbance set up: a three-phase fault on Bus 4 at 0.1 seconds. The fault clears at 0.18 seconds when Line 4-5 is switched out. To see it:

  1. On the Calculate tab, under Dynamics, select Events.
  2. Read the 3 events: Three-phase fault at, Clear fault at and Switch out.
  3. Select Cancel to close the dialog without changing anything.

Now run it:

  1. On the Calculate tab, select Simulation, or press Alt+R.
  2. In the results panel's Stability tab, read the result. It says All machines stay in synchronism.
  3. To plot something else, choose it from the list at the top right of the tab, such as Speed or Active power.
  4. Select a machine in the legend to hide or show it.

To see how much margin there is:

  1. Open Events again.
  2. Change the time of the Clear fault at and Switch out events so the fault lasts longer.
  3. Run the simulation again.

Read more in Check machines stay in step.

Look at the first cycles of the fault

The stability simulation follows swings over seconds. An electromagnetic transient (EMT) simulation shows the first cycles instead. A cycle is 1 period of the supply frequency: 20 ms at 50 Hz. The simulation gives the voltage and current of each phase, sample by sample.

The sample has an EMT disturbance too: a three-phase fault on Bus 4 at 20 ms. It clears at 100 ms, when Line 4-5 trips. To see it:

  1. On the Calculate tab, under Dynamics, select EMT events.
  2. Read the 3 events: Fault at, Clear fault at and Trip.
  3. Select Cancel to close the dialog.

Now run it:

  1. On the Calculate tab, select EMT, or press Alt+W.
  2. Read the EMT tab in the results panel. It says 200 ms simulated.
  3. In the Waveforms view, select Bus 4 on the diagram. The plot shows its 3 phase voltages.
  4. Drag across the plot to zoom in on a time range. Double-click to show the whole run.

The voltage of Bus 4 falls when the fault starts at 20 ms. Look at the other views for the numbers:

To try a fault at another busbar, right-click it and select Add fault to EMT simulation. This adds a line-to-earth fault that you can edit under EMT events.

Warning: EMT is not a grid code compliance tool. It holds every source's voltage at its load-flow value, so use it for the first few hundred milliseconds only. Use the stability simulation for anything longer.

Read more in Look at the first cycles of a fault or switching. The method is in the EMT section of the engine reference.

Export and compare results

Export a table. You can save every table in the results panel as a CSV file to open in a spreadsheet. Show the table you want, then select Export table as CSV. The button is at the top right of the results panel. The command is also on the Calculate tab.

Compare 2 runs. PowerStudio records every calculation you start in the project's run log. To compare the summer load flow with the winter one:

  1. Switch to the Winter peak study case.
  2. Run the load flow (Alt+L).
  3. Switch to the Summer minimum study case.
  4. Run the load flow again.
  5. In the Load flow tab, open Compare with a recorded run….
  6. Choose the latest run marked Winter peak.

The table now shows the difference from that run beside each value, such as ΔLoading for branches. Select Changed to show only the rows that differ.

The run log records only the calculations you start yourself. It does not record the ones that Recalculate on edit runs.

Keep a copy. PowerStudio saves your work in this browser. To keep a copy somewhere else, or to move it to another computer:

  1. Go to File, then Export.
  2. Choose Project.

Study report gives you a report to print or save as a PDF. Encrypted project locks the copy with a passphrase.

Read more in Work with results and Save, share and protect your work.

Find where to start each study

If you want toStart hereRead more
Check voltages and loadings at one operating pointLoad flow (Alt+L)Run a load flow
Check the fault level against switchgear ratingsShort circuit with Maximum currentsFind fault levels
Find the lowest fault currents, for protectionShort circuit with Minimum currentsFind fault levels
Check the network survives the loss of any 1 circuitContingency (Alt+N)Check the network survives outages
Check machines stay in step after a faultEvents, then Simulation (Alt+R)Check machines stay in step
Look at the first cycles of a fault or switchingEMT events, then EMT (Alt+W)Look at the first cycles of a fault or switching
Compare seasons or operating conditionsA scenario and a study case for eachSet up study cases, scenarios and variants
Study a planned reinforcement, such as a new lineA variant, switched on in a study caseSet up study cases, scenarios and variants
Change the data of many elementsThe Data tab in the results panelEnter element data
Draw your own networkThe Insert tabBuild your network
Use a model from another tool (CGMES, PSS/E, MATPOWER)File, then ImportImport a model from another tool
Share resultsFile, then ExportSave, share and protect your work
Compare PowerStudio's results with your own tool'sThe ps compare commandCheck PowerStudio against your own tool